By Our Reporter 

The Transmission Company of Nigeria (TCN), Lagos Region, has successfully commissioned a new 300MVA power transformer at its 330/132/33kV Egbin Transmission Substation in Lagos State on February 22, 2025.


With this development, the substation’s capacity has increased from 300MVA to 450MVA, significantly boosting bulk power availability for Ikeja Electricity Distribution Company (IKEDC). The enhanced capacity will enable the distribution company to deliver improved electricity supply to customers in Ikorodu, Shagamu, Ijede, and surrounding communities.


The General Manager (Transmission), Lagos Region, Engr. Adeshina Adeonipekun, described the project as a major milestone in TCN’s ongoing efforts to strengthen the national transmission grid. He noted that the installation was executed in-house by TCN engineers and completed within a record six weeks, underscoring the company’s technical capability and commitment to improving power delivery across the country.