The Federal Ministry of Water Resources has disclosed that the delay in the connection of power transmission lines to the national grid was responsible for non-completion of the Kashimbilla Multipurpose Dam in Taraba.
The Acting Director, Dams and Reservoir Operations in the ministry, Mr Lawal Muhammad, said this on Friday in an interview with News Agency of Nigeria (NAN) in Abuja. Muhammad said that the dam and the power generating components of the project had been completed. He said that the outstanding aspect of the project was the erection of power transmission lines that would convey electricity to the national grid, adding, however, that this was the responsibility of the Federal Ministry of Power, Works and Housing.He said that work on water supply component of the dam had gone far, while work on the reticulation network had reached an advanced stage.
Muhammad said that the irrigation component of the dam had been designed, while work on it had also reached an advanced stage.
“The dam was identified by the United Nations (UN) as one of the key projects that we need to do to provide a buffer against flooding along the River Benue, which of course you remember in 2012 was quite devastating.
“Certainly, flood around the River Benue has always been a recurring decimal, in view of the dams which have been constructed by Cameroon. Whenever water is released unsystematically, it continues to cause a lot of damage.’’
Adamu stressed that the Federal Government was more committed to completing all ongoing dam projects across the country, rather than embarking on the construction of new ones. He said that the Federal Government was also not in a hurry to take up new water projects, adding that the construction of new dams invariably involved a lot of planning and design.