FCDA road dualization project: TCN restores bulk power to Apo Transmission Substation 

Share this article

By Oke Peter

The Transmission Company of Nigeria (TCN) has announced the restoration of full bulk power to its 132/33kV Apo Transmission Substation, effective Thursday, January 23, 2025.

This restoration follows the successful relocation of eight 132kV and 33kV towers along the Kukwaba/Apo 132kV line (Southern Expressway route), necessitated by the Federal Capital Development Agency’s (FCDA) road dualization project along the Apo axis.

The two-week relocation work, which commenced on Monday, January 6, 2025, involved dismantling, and reconstructing the towers, as well as restringing power cables.

Transformer

With the restoration of full bulk power, Abuja DisCo can now provide normal electricity supply from the substation to its customers in the affected areas, ending the previous load rationing.

The Company appreciates the patience and understanding of the affected electricity consumers during this period.


Share this article

2 thoughts on “FCDA road dualization project: TCN restores bulk power to Apo Transmission Substation 

  1. 有道词典是由网易有道出品的全球首款基于搜索引擎技术的全能免费语言翻译软件。简介. 支持中文、英语、日语、韩语、法语、德语、俄语、西班牙语、葡萄牙语、藏语、西语等109种语言翻译。拍照翻译、语音翻译、对话翻译、在线翻译、离线翻译更顺畅。更多的翻译 https://www.fanyim.com

Leave a Reply

Your email address will not be published. Required fields are marked *